PT Inco: May 2010 exploration report

Wednesday, June 9 2010 - 08:04 AM WIB

(Jakarta, June 9, 2010) ? PT International Nickel Indonesia Tbk (?PT Inco?) is reporting that the exploration activities for the month of May 2010 continue by focusing on areas inside the Contract of Work area.

Exploration Area : Konde, Sorowako area in East Luwu Regency, South Sulawesi

Total Cost : Approximately US$ 32,400

Exploration Method : The Konde Project uses the core drilling HQ-3 method for geostatic drilling program and space 25m

Exploration Contractor : Sorowako Project is jointly carried out by PT Inco and third parties

Testing results : Testing results are in the process of reserve estimation calculation by using block modeling method in Sorowako

Action Plan :
- Sorowako Project Area 25m spaced drilling continued in Konde and Petea (Sorowako area) with 20 rigs and 4 rigs
- All drillings are planned to obtain complete literate profile. (end of release)