PT PLN?s invitation for selected providers of IPP renewable energy power plants
Friday, October 13 2017 - 09:15 AM WIB
INVITATION FOR LIST OF SELECTED PROVIDERS (DAFTAR PENYEDIA TERSELEKSI/ DPT) FOR IPP (INDEPENDENT POWER PRODUCERS) RENEWABLE ENERGY POWER PLANTS
1. PT PLN (Persero) intends to select a potential project sponsor which will be list on Selected Providers (Daftar Penyedia Terseleksi / DPT) to develop IPP Renewable Energy Power plants. As per Ministry of Energy and Mineral Resources Regulation No. 50 / 2017, the Procurement Process of IPP Renewable Energy Power plants will be held with direct selection mechanism from a pool of Qualified Applicants listed on Selected Providers (as the case maybe update from time to time) (Daftar Penyedia Terseleksi / DPT) that meet criteria on Pre-Qualification Quesionnaire Document.
2. The project for IPP Renewable Energy Power plants are Solar PV, Hybrid Energy, Wind Energy, Biomass, Biogass, Municipal Waste and Tidal Wave (the ?Project?), which will be implemented on BOOT (Build, Own, Operate & Transfer) pursuant to a long term Power Purchase Agreement (PPA).
3. PT PLN (Persero) hereby invites interested Parties who have intention to be qualified and included on Selected Providers List (Daftar Penyedia Terseleksi / DPT) for development of IPP Renewable Energy (RE) Power plants:
Title: DAFTAR PENYEDIA TERSELEKSI (DPT)
RE Power plant Type: Solar PV, Hybrid Energy, Wind Energy, Biomass, Biogass, Municipal Waste and Tidal Wave.
The interested Party have to submit application and state type of RE power plant that will be applied, in accordance with Pre-Qualification Quesionnaire Document,
4. The interested Party shall be a company from Indonesia or Country which has diplomatic relation with Indonesia. The Qualified Applicant will be required to incorporate Special Purpose Company among the listed Qualified Applicant on Selected Providers. In accordance with Laws of Indonesia, if a Party is foreign company, they shall engage with reputable local company for Special Purpose Company incorporation in order to execute Power Purchase Agreement.
For qualification, the Parties must demonstrate that they have experience in implementing at least 1 (one) IPP Contract, EPC Contract and/or O&M Contract which has been completed within the last 10 (ten) years and achieved satisfactory records for one (1) years operation for each unit of Power Plant.
In addition, the interested Parties shall fulfill financial requirement as set forth in the Pre-qualification Questionnaire Document, whereas for each criteria / requirement, the interested Parties shall submit evidence on their application with a recent valid document.
5. The interested Parties, which represented by its authorized person, may respond with intent to register the Pre-qualification Questionnaire Document from October 18th 2017 - October 27th2017 (working hours from 08.00 - 16.00 West Indonesian Standard Time), after payment of a non refundable fee in the amount of Rp 10,000.000,- (ten million Rupiah) at the address below:
PT PLN (Persero) Head Office
c/o Chief of Procurement Committee for List of Selected Providers
Main Building, 13th Floor, Jalan Trunojoyo Blok MI/135, Kebayoran Baru, Jakarta12160
Phone +6221-7251234, 7261122,Ext. 1175
Fax +6221-7227063
6. The Application shall be submitted in one (1) original, one (1) copy and one (1) electronic copy by hand not later than 15:00 PM local time on November 14th, 2017 to the above address in the sealed envelopes with clearly marked the type of power plant as mentioned as Project.