Regional: Hyundai signs EPC contract for Mong Duong power plant
Monday, September 19 2011 - 06:22 AM WIB
The US$1.274 billion agreement formed part of the national electricity development programme in the period 2006-15, approved by Prime Minister Nguyen Tan Dung, which applied to coal-powered plants in Mong Duong Ward in Quang Ninh Province, 250km north-east of Ha Noi.
Covering an area of 55hectares, the 1,080-MW Mong Duong 1 Thermopower Plant was expected to generate 6.5 billion KWh annually.
The plant would use coal with thermopower technology suitable for Viet Nam's low-quality anthracite coal.
This technology has a high capacity with low costs, in addition to ensuring environmental protection.
The plant would consume about 3 million tonnes of coal per year.
The plant's first turbine was expected to become operational in the first quarter of 2015, with a second to follow in the third quarter of 2015. (*)