Release: Archipleago Resources: Toka Tindung gold project- Construction progress update
Thursday, October 12 2006 - 03:19 PM WIB
Construction:-
Three dams and associated drainage structures have been constructed during the past few months of the dry season as part of a previously announced US$3.5 million civil earthworks contract awarded to Leighton Contractors Indonesia.
Reinforced concrete foundations are now being constructed for the primary crusher, crushed ore reclaim tunnel, mills and processing plant as part of a previously announced US$2.2 million tender awarded to Bakrie Constructions.
The purchase of land necessary to commence the project has been completed and a 7km road has been constructed from the processing plant to the coast where a jetty for delivery of large items of processing plant and bulk operating consumables will be constructed in coming months.
A road leading from the highway to the site access road has been sealed to further improve the already good road access enjoyed by the project.
Shipment of Processing Plant:-
Containerised components of the El Tambo processing plant were despatched from Chile on 1 October 2006. The containers are scheduled to arrive in Indonesia in November, apart from electrical control equipment which is being shipped to Perth for refurbishment. A final shipment containing bulk processing plant equipment is scheduled to depart Chile in November 2006 and is expected to arrive in Indonesia around the end of this year.
Employment:-
Employment numbers at the Toka Tindung Gold Project have now risen to 600 employees, the majority of whom reside in villages surrounding the project area. The total construction workforce is expected to peak at close to double this number by the middle of next year.
The Toka Tindung Gold Project has a resource of 1.7M ounces (ozs) of gold, of which at least 0.9M ozs will initially be mineable by open pit. The project is targeted to commence production at the rate of 140,000 ozs per annum increasing to a target of 160,000 ozs per annum in subsequent years. Subject to continuing progress with operating permits, production remains on schedule to commence in the third quarter of 2007.
Archipelago is a mining company listed on the AIM market of the London Stock Exchange. The Company?s principal activities are gold mining and exploration in Indonesia (as 85% owner of the Toka Tindung Gold Project in Sulawesi), Vietnam (as majority party in the Pac Lang and Cam Thuy/Ba Thuoc joint ventures with Vimico a Vietnamese Government mining company) and the Philippines (as option holder over a 100% interest in the Corplex tenements).(end of release)