Release: Seram's Oseil production operations update
Wednesday, March 12 2003 - 02:57 AM WIB
Production from the Oseil oilfield commenced on December 30th 2002, with processing taking glace through a Temporary Production System (?TPS?) nominally rated to approximately 12,000 barrels per day throughput.
The TPS facility is a temporary process facility to be utilized until the permanent facilities currently being installed are completed. Current expectations are that the permanent facilities will be available during April 2003.
REPORTING PERIOD |
From midnight 2nd March 2003 To midnight 9th March 2003 |
Oil produced for the period |
66,941 barrels of oil |
Average daily production for the period |
9,563 barrels of oil |
Cumulative oil produced |
590,838 barrels of oil |
| Oil sold during the period | 296,557 barrels of oil |
| Oil in stock | 52,982 barrels of oil |
COMMENTS
All three wells Oseil #1, Oseil #2 and Oseil #4 on production. Current operations are continuing production through the TPS system.
Your faithfully,
Guiseppe (Joe) Mercorella; CHAIRMAN KALREZ ENERGY LTD