Santos Indonesian drilling update

Thursday, September 15 2005 - 07:16 AM WIB

The following is excerpt from Santos Limited?s Weekly Drilling Report for week ending September 15, 2005:

Delineation Well(Near Field Exploration/ Appraisal Well)Jeruk 2 ST4/ST5
TypeOil Appraisal
LocationOffshore Indonesia
Sampang PSC, East Java Basin. 1.6km E of Jeruk 1, 35.0km SW of the Oyong Field, and some 40km SE of Surabaya. Jeruk 2 ST4/ST5 are an appraisal sidetrack drilled out of the existing Jeruk 2 wellbore.
Status at 0300hrs -- 15/09/05 Jeruk 2 ST5 has been suspended following the completion of production testing (as previously reported). The well reached a total depth of 5102m with no progress for the week. The rig was released on 14/09/05.
Planned Total Depth5080m
InterestSantos Group 45.0%
Singapore Petroleum Sampang Ltd 40.0%
Cue Sampang Pty Ltd 15.0%
OperatorSantos Group

-------------------------------------------

Development WellWunut 16
TypeGas Development
LocationOnshore Indonesia
Brantas PSC, East Java Basin. 0.5km NE of Wunut 9, and some 30km S of Surabaya.
Status at 0600hrs -- 15/09/05 Continuing cased hole production testing operations. Wunut 16 reached a total depth of 930m with no progress for the week. Production testing over the perforated intervals 700m-707m and 627m-632m flowed gas at 93450 cubic meters per day (3.3mmcfd) and 62300 cubic meters per day (2.2 mmcfd) respectively, through a 9.5mm (24/64?) surface choke. A further cleanup flow from the perforated interval 800m-807m flowed gas at 28300 cubic meters per day (1.0 mmcfd). The well has been completed as a gas producer and the rig was released on 14/09/05.
Planned Total Depth930m
InterestLapindo Brantas 50%
Novus Indonesia Brantas Company 32%
Santos Group 18%
OperatorLapindo Brantas

-------------------------------------------

Development WellOyong Development
TypeOil Development
LocationOffshore Indonesia, East Java Basin
Sampang PSC, 40km E of Jeruk 1 and some 80km E of Surabaya. 7 Deviated Well Batch Drilling Program (Oyong 4 DW1 ? Oyong 10 DW1)
Status at 0600hrs -- 15/09/05 Setting abandonment plugs in Oyong-8 DW1 pilot hole. Preparing to drill horizontal development well.
Oyong 4 DW1/ST1: Well completed. 178mm casing set at 1230m. TD 1610m.
Oyong 5 DW1: 244mm casing set at 965m. Depth 1296m. PBTD 870m.
Oyong 6 DW1 Pilot: 244mm casing set at 1022m. Hole abandoned at 1200m.
Oyong 7 DW1/ST1: Well completed. 178mm casing set at 1189m. TD 1680m.
Oyong 8 DW1: 244mm casing set at 1351m. TD 1652m. Well Abandoned for sidetrack
Oyong 9 DW1/ST2: 244mm casing set at 1416m. TD 1474m. Pending completion.
Oyong 10 DW1: 244mm casing set at 835m. Current depth 838m.
Planned Total Depth920m SS
InterestSantos Group 45.0%
Singapore Petroleum Sampang Ltd 40.0%
Cue Sampang Pty Ltd 15.0%
OperatorSantos Group
Share this story