Santos Indonesian drilling update

Thursday, September 22 2005 - 08:03 AM WIB

The following is excerpt from Santos Limited?s Weekly Drilling Report for week ending September 22, 2005:

Development WellOyong Development
TypeOil Development
LocationOffshore Indonesia, East Java Basin
Sampang PSC, 40km E of Jeruk 1 and some 80km E of Surabaya. 7 Deviated Well Batch Drilling Program (Oyong 4 DW1 ? Oyong 10 DW1)
Status at 0600hrs -- 22/09/05 Conditioning hole in Oyong-8 DW1ST2 prior to drilling ahead from 962m.
Oyong 8DW1ST1 was abandoned after the hole packed off at 540m.

Oyong 4 DW1/ST1: Well completed. 178mm casing set at 1230m. TD 1610m.
Oyong 5 DW1: 244mm casing set at 965m. Depth 1296m. PBTD 870m.
Oyong 6 DW1 Pilot: 244mm casing set at 1022m. Hole abandoned at 1200m.
Oyong 7 DW1/ST1: Well completed. 178mm casing set at 1189m. TD 1680m.
Oyong 8 DW1: 244mm casing set at 1351m. TD 1652m. Pilot hole abandoned to drill sidetrack production well.
Oyong 8 DW1ST1: Well abandoned after reaching a depth of 832m.
Oyong 9 DW1/ST2: 244mm casing set at 1416m. TD 1474m. Pending completion.
Oyong 10 DW1: 244mm casing set at 835m. Current depth 838m.
Planned Total Depth920m SS
InterestSantos Group 45.0%
Singapore Petroleum Sampang Ltd 40.0%
Cue Sampang Pty Ltd 15.0%
OperatorSantos Group

Share this story