Australian-based oil and gas firm Santos Limited has released on Friday its 2016 firsth quarter report. The following is an edited excerpt of the report on the company?s oil and gas production in Indonesia.

Production
Santos? net entitlement to gas production of 6.0PJ was 7% higher than the corresponding period. Net entitlement gas production from the Madura PSC was in line with the corresponding quarter due to increased contractor entitlement in Peluang and Maleo, offset by decreased gross production volumes which averaged 63 TJ/day for the quarter.

Santos? net entitlement to gas production from the Sampang PSC increased by 18% primarily due to planned shutdown activity at Oyong for workover activities during the corresponding quarter.

Oyong net entitlement oil production for the quarter was 33,800barrels. (end of edited excerpt)