Seven upstream projects to be on-stream in 2018
Saturday, December 30 2017 - 03:25 AM WIB
Upstream oil and gas authority SKK Migas said that there will be seven upstream oil and gas projects targeted to be on-stream in 2018.
Deputy for Procurement Control at SKK Migas, Djoko Siswanto told Petromindo.com on Friday that the seven upstream projects are as follows.
1. PT Medco E&P Malaka Indonesia: Lica Production Facility Optimization Project with production facility capacity of 4,000 bopd, peak production estimate of 3,700 bopd, and on stream target in March 2018.
2. PT Medco E&P Malaka: Block A Gas Field Development Project with production facility capacity of 3,100 bopd, and peak production estimate of 55 mmscfd and 3,100 bopd, which is targeted to be on stream in March 2018.
3. PT PHE ONWJ: SP Project with production facility capacity of 30 mmscfd, and peak production estimated of 30 mmscfd, and targeted to start production in September 2018.
4. PetroChina Intl. Jabung Ltd.: CPS Modification Project with production facility capacity of 30 mmscfd, and peak production estimated of 30 mmscfd, and targeted to be on stream in December 2018.
5. PT Tropik Energi Pandan: Ario Damar-Sriwijaya Phase 2 Project with production facility capacity of 20 mmscfd, peak production estimate of 20 mmscfd, and on-stream target in December 2018.
6. PT Medco E&P Indonesia: Transmission of Temelat Gas to Gunung Kembang Station Project with production capacity of 13 mmscfd, peak production estimate of 10 mmscfd, and on-stream target in December 2018.
7. PT Pertamina EP: Construction of Subsea Pipeline Gas Lift BW Field Poleng with production capacity of 700 mmscfd, and peak production estimate of 700 mmscfd, and on-stream target in December 2018.
Editing by Reiner Simanjuntak