Shaw awarded Kamojang EPC contract
Thursday, March 23 2006 - 01:21 AM WIB
The plant, which will be located in Kamojang, West Java, is the first Pertamina independent power project to sell electricity to Indonesia's national electric power utility, PLN. The work will be done in conjunction with PT Rekayasa, a construction company headquartered in Jakarta, Indonesia, and is scheduled to be completed in 2008.
Shaw is also working with Pertamina on other feasibility studies for geothermal projects in Indonesia, which has a geothermal resource potential of over 20,000 megawatts, the company said.
The company had previously executed several projects in Indonesia including the Suralaya coal-fired power plant, Darajat Stage II Geothermal Power Plant, North Duri Cogen Power Plant and others. (alex)