Sonoro begins construction at W. Sulawesi appraisal well project

Thursday, June 22 2017 - 05:18 AM WIB

By Alexander Ginting

Calgary-based junior oil, gas firm Sonoro Energy Ltd reported on Thursday that it has engaged local contractors to commence construction of the LG-1 updip well location in Budong Budong PSC, onshore West Sulawesi.

Clearing of the road and site began on Saturday, June 17, and as of Tuesday, June 20, approximately 50% of the road and lease construction had been completed.

The Company has also made progress in finalizing remaining drilling services, and expects that by the end of this week all letters of intent will be completed, with contracts then to be finalized. With this progress, the Company remains on schedule to commence drilling in early August, it said.