Suralaya gets coal supply commitment from Kalimantan producers: Update

Friday, February 6 2004 - 08:19 AM WIB

A government official confirmed on Friday that four Kalimantan-based coal producers have committed to supply their products to its Suralaya coal-fired power plant in Banten province.

?Suralaya will get a total of around 1.7 million tons (of coal) from Adaro, Arutmin, Kideco and Berau Coal in February ? April period,? Geology and Mineral Resources Director General Simon F. Sembiring told Petromindo.Com.

Simon said Suralaya would consume around 2.9 million tons of coal during the period. ?Another 1.2 million tons would be provided by its main supplier PT Tambang Batubara Bukit Asam,? he said. (alex/godang)