Table: 10 PSCs unable to meet production targets
Thursday, March 24 2011 - 10:15 AM WIB
| No. | Contractor(s) | Deviation (BOPD) | Issues |
| 1. | Kodeco | 12,000 | 1. Status of production sharing contract after May 2011 |
| 2. Demand for Direct Appointment in the procurement of rig | |||
| 2. | Chevron Pacific Indonesia | 11,800 | 1. Oil condensing in pipe thus closing well, which causes the production to decrease by 33,000 BOPD |
| 2. Steam injection stops during pipe leakage. | |||
| 3. | Pertamina EP | 9,800 | 1. Damage of lifting pipe in Udang Field |
| 2. Well BN 18 in Bunyu field died | |||
| 3. Water injection in Talang Field, environmental issue | |||
| 4. | ConocoPhillips Block B | 9,500 | Production stops because failure in safety alarm system remains unknown. |
| 5. | Total E&P Indonesie | 7,000 | The incoming and outgoing of rig upon drilling, which requires the closure of production well |
| 6. | JOB P. Golden Spike | 2,800 | Lateness in the execution of drilling due to internal issue of the partner. |
| 7. | CNOOC | 2,500 | Leakage in distribution pipe from Karmila to Titi Field |
| 8. | Sele Raya Merangin | 2,000 | Restriction of trucking capacity by Musi Rawas Regional Government. |
| 9. | JOB P. Medco Tomori | 1,700 | Cendana Putra Field remains unable to produce, pending the readiness of gas buyer. |
| 10. | BOB P. Bumi Siak Pusako | 900 | 1.Reparation of well is delayed due to flooding |
| 2. Provision of electricity for the long term has not been realized. | |||
Source: BPMIGAS |
|||