Table: 10 PSCs unable to meet production targets

Thursday, March 24 2011 - 10:15 AM WIB

No. Contractor(s) Deviation (BOPD) Issues
1. Kodeco 12,000 1. Status of production sharing contract after May 2011
2. Demand for Direct Appointment in the procurement of rig
2. Chevron Pacific Indonesia 11,800

1. Oil condensing in pipe thus closing well, which causes the production to decrease by 33,000 BOPD

2. Steam injection stops during pipe leakage.
3. Pertamina EP 9,800

1. Damage of lifting pipe in Udang Field

2. Well BN 18 in Bunyu field died
3. Water injection in Talang Field, environmental issue
4. ConocoPhillips Block B 9,500 Production stops because failure in safety alarm system remains unknown.
5. Total E&P Indonesie 7,000 The incoming and outgoing of rig upon drilling, which requires the closure of production well
6. JOB P. Golden Spike 2,800 Lateness in the execution of drilling due to internal issue of the partner.
7. CNOOC 2,500 Leakage in distribution pipe from Karmila to Titi Field
8. Sele Raya Merangin 2,000 Restriction of trucking capacity by Musi Rawas Regional Government.
9. JOB P. Medco Tomori 1,700 Cendana Putra Field remains unable to produce, pending the readiness of gas buyer.
10. BOB P. Bumi Siak Pusako 900

1.Reparation of well is delayed due to flooding

2. Provision of electricity for the long term has not been realized.

Source: BPMIGAS