Table: Gas lifting as of April 2019
Friday, May 10 2019 - 03:59 AM WIB
Following is the gas lifting of PSC holders from January through April 2019
|
No |
Contractors |
Year 2019 (status in April 30, 2019) |
Notes |
|||
|
Budget Lifting Target (mmscfd) |
Realized Production (mmscfd) |
Realized Lifting (mmscfd) |
Lifting Realization vs Budget (%) |
|||
|
1 |
BP BERAU LTD |
1,050 |
1,148 |
912 |
87% |
Occurrences of trips in January and March 2019, and currently recovering |
|
2 |
PERAMINA HULU MAHAKAM |
1,100 |
725 |
667 |
61% |
Higher decline rate by end of 2018, and several wells already drilled not yet online |
|
3 |
CONOCOPHILLIPS (GRISSIK)LTD. |
810 |
1,028 |
834 |
103% |
|
|
4 |
PT.PERTAMINA EP |
810 |
965 |
770 |
95% |
Higher decline rate by end of 2018 |
|
5 |
ENI MUARA BAKAU |
645 |
633 |
620 |
96% |
Waiting for progress of infill drilling to give maximum result |
|
6 |
JOB PERTAMINA –MEDCO TOMORI SULAWESI LTD |
300 |
343 |
329 |
110% |
|
|
7 |
PREMIER OIL INDONESIA |
220 |
219 |
207 |
94% |
Fluctuation of absorption level by consumers |
|
8 |
KANGEAN ENERGI INDONESIA |
200 |
118 |
109 |
55% |
Tie-in project of Sirasun and Batur just start running and under progress of ramp-up |
|
9 |
MEDCO E&P NATUNA |
165 |
215 |
176 |
107% |
|
|
10 |
PETROCHINA INTERNATIONAL JABUNG LTD |
161 |
283 |
174 |
108% |
|
|
Other contractors |
1,539 |
1,544 |
1,111 |
72% |
|
|
|
TOTAL |
7,000 |
7,221 |
5,909 |
84% |
|
|
|
Source: SKK Migas |
||||||