COD

1 BALI Geothermal

Bedugul

10

2012

2 W. JAVA Geothermal Darajat 20 2012
3 W. JAVA Geothermal Wayang Windu 110 2012
4 W. JAVA Geothermal Karaha Bodas 30 2012
5 C. JAVA Geothermal Dieng 55 2012
6

W. JAVA

Geothermal Kamojang 60 2013
7 W. JAVA Geothermal Cibuni 10 2013
8 W. JAVA Geothermal Patuha 180 2013
9 W. JAVA Geothermal Salak 40 2013
10 W. JAVA Geothermal Darajat 55 2013
11 W. JAVA Geothermal Wayang Windu 70 2013
12 C. JAVA Geothermal Dieng 60 2014
13 W. JAVA Geothermal G.Tangkuban Perahu 1 110 2014
14 W. JAVA Geothermal Cisolok-Cisukarame 30 2014
15 C. JAVA Geothermal Ungaran 55 2014
16 W. JAVA Geothermal Karaha Bodas 110 2014
17 E. JAVA Geothermal Ijen 30 2014
18 E. JAVA Geothermal Wilis/Ngebel 110 2014
19 C. JAVA CSTPP C. Java Infrastructure 2,000 2014
20 W. KALIMANTAN CSTPP Sintang 10 2011
21 W. KALIMANTAN CSTPP Sintang 10 2012
22 W. KALIMANTAN CSTPP Ketapang 10 2012
23 W. KALIMANTAN CSTPP Ketapang 10 2012
24 C. KALIMANTAN CSTPP Pangkalan Bun 7 2010
25 C. KALIMANTAN CSTPP

Pangkaan Bun

7 2010
26 EAST KALIMANTAN CSTPP

Berau

10 2011
27 EAST KALIMANTAN CSTPP Melak 5 2011
28 EAST KALIMANTAN CSTPP Nunukan 6 2011
29 EAST KALIMANTAN CSTPP Melak 5 2012
30 EAST KALIMANTAN CSTPP Nunukan 6 2012
31 MALUKU CSTPP Ambon 6 2010
32 MALUKU CSTPP Ternate 6 2010
33 MALUKU CSTPP

Ternate

6 2010
34 MALUKU CSTPP Ambon 6 2011
35 NTB CSTPP Lombok 25 2011
36 NTB CSTPP Lombok 25 2012
37 NTT CSTPP Kupang 15 2011
38 NTT CSTPP Kupang 15 2011
39 PAPUA CSTPP Jayapura 11 2011
40 PAPUA CSTPP Jayapura 11 2011
41 SE. SULAWESI CSTPP Bau-Bau 7 2010
42 SE. SULAWESI CSTPP Bau-Bau 7 2010
43 SOUTHERN PART OF SUMATRA Geothermal Kerinci 20 2011
44 SOUTHERN PART OF SUMATRA Geothermal Rajabasa 55 2012
45 SOUTHERN PART OF SUMATRA Geothermal Rajabasa 55 2013
46 SOUTHERN PART OF SUMATRA Geothermal Wai Ratai 55 2014
47 NORTHERN PART OF SUMATRA Geothermal Sipaholon 30 2012
48 NORTHERN PART OF SUMATRA Geothermal Sorik Merapi 55 2012
49 NORTHERN PART OF SUMATRA Geothermal Pusuk Bukit 55 2014
NOTE: CSTPP=COAL FIRED POWER PLANT; COD=COMMERCIAL OPERATIONAL DATE