No. Name of power plants Region Type Capacity (MW) Developer Next Progres
1. Kuala Tungkal Sumatera PLTU 2 x 7 PT. ZUG Industri Indonesia Now under process of terminating contract. Replacement: developing PLTG/MPP Tanjung Jabung 30 MW, Planned operation 2018 and development of GI in the region.
2. Ipuh Seblat Sumatera PLTU 2 x 3 Consortium of Amarta Karya (Persero), Pt. Rimbanusa Pikantimnas Now under process of terminating contract. Replacement: developing PLTG/MPP Muko Muko 30 MW which is now under preparation for tender, planned operation 2018 and development of GI in the region.
3. Tembilahan Sumatera PLTU 2 x 5,5 PT. Eksploitasi Energi Indonesia Already terminated. As replacement will be development of PLTG/MPP Tembilahan 30 MW. Planned operation 2018 and development of GI in the region.
4. Raha Sulawesi & Nusa Tenggara PLTU 2 x 3 PT. Hutama Karya (Persero) Replaced with GI 150 KV/20 Kv capacity 60 MVA, target of COD in 2018
5. Wangi Wangi Sulawesi & Nusa Tenggara PLTU 2 x 3 PT. Hutama Karya (Persero) To be replaced with PLTMG/G capacity 5 MW which is under tender process and target of COD 2017
6. Kaltim (FTP 2) Kalimantan PLTU 2 x 100 Pt. Graha Power Kaltim Under process of verifying documents of financing date. Target of Financing verification by end of January 2017
7. Kalsel (FTP 2) Kalimantan PLTU 2 x 100 PT. Tanjung Power Indonesia Under process of achieving financing date with target of Financing Close on Jan.24, 2017, but still awaiting government guarantee.