Table: Oil and gas projects already onstream this year

Thursday, May 9 2019 - 10:26 AM WIB

The following is the list of oil and gas projects already onstream in 2019 as unveiled by SKK Migas

No

Project name

Contractors

Status by April 2019

Onstream Target

1.

Seng Segat

(Production estimation: 60 MMscfd)

EMP Bentu Ltd.

97.08% (Actual)

(Investment estimation:US$ 62 million)

May 2019 (Q2)

2.

Ario-Damar-Sriwijaya Phase-2

(Production estimation: 20 MMscfd)

PT. Tropik Energi Pandan

 

80.59% (Actual)

(Investment estimation:US$ 11 million)

July 2019 (Q3)

3.

Suban Compression

(Production estimation: 100 MMscfd, to keep  existing production at around 780 MMscfd)

ConocoPhillips (Grissik) Ltd.

 

96.57% (Actual)

(Investment estimation:US$ 440 million)

 

August 2019 (Q3)

4.

YY

(Production estimation: 4,605 bopd (OIL),25.5 MMscfd (GAS))

PHE ONWJ

 

79.12% (Actual )

(Investment estimation:US$ 56 million)

 

October 2019 (Q4)

5.

Bukit Tua Phase-3

(Production estimation: 3,182 bopd (OIL),31 MMscfd (GAS))

Petronas Carigali Ketapang II Ltd.

 

69.89% (Actual)

(Investment estimation:US$ 15 million)

 

November 2019 (Q4)

6.

Buntal-5

(Production estimation: 45 MMscfd)

Medco E&P Natuna Ltd.

 

38.04% (Actual)

(Investment estimation:US$ 33 million)

November 2019 (Q4)

7.

Bison-Iguana-Gajah Puteri

(Production estimation: 80 MMscfd)

Premier Oil Natuna Sea B.V

37.75% (Actual)

(Investment estimation:US$ 171 million)

November 2019 (Q4)

8.

Temelat

(Production estimation: 10 MMscfd)

PT. Medco E&P Indonesia

58.30% (Actual)

(Investment estimation:US$ 11 million)

November 2019 (Q4)

9.

Panen

(Production estimation: 2000 bopd)

PetroChina International Jabung Ltd.

On preparation stage of land and PO Pipe

(Investment estimation:US$ 17 million)

November 2019 (Q4)

10.

Kedung Keris

(Production estimation: 3,800 bopd)

ExxonMobil Cepu Ltd.

 

26.26% (Actual)

(investment estimation:US$ 72 million)

December 2019 (Q4)

Source: SKK Migas

 