Table: Oil and gas projects scheduled to come onstream in second semester of 2014
Wednesday, August 20 2014 - 05:01 AM WIB
The following is the list of oil and gas projects scheduled to come onstream in second semester of 2014 as unveiled by SKK Migas
| No | Proyek | Operator(s) | Onstream | Installed Capacity |
| 1 | Bayan-Gas Field Development | Manhattan Kalimantan Investment Pte. Ltd. (MKI) | Q4 - 2014 | Gas: 15 MMSCFD |
| Oil: 250 BPD | ||||
| 2 | Kerendan Gas Plant | Salamander Energy (Bangkanai) Ltd. | Q4 - 2014 | Gas: 25 MMSCFD |
| Liquid: 300 BPD | ||||
| 3 | Simenggaris Gas Plant | JOB Pertamina - Medco Simenggaris Pty. Ltd. | Q4 - 2014 | Gas: 25 MMSCFD |
| Liquid: - | ||||
| 4 | SES Gas Development (Mila-A and Asti-A) | CNOOC SES | Q3 - 2014 | Gas: 80 MMSCFD |
| Liquid: - | ||||
| 5 | Beringin Field (POFD) | PT Pertamina EP | Q4 - 2014 | Gas: 20 MMSCFD |
| Liquid: 1000 BPD | ||||
| 6 | Kepodang Development | Petronas Carigali Muriah | Q4 - 2014 | Gas: 116 MMSCFD |
| Liquid: - | ||||
| 7 | Full Scale South Belut | Conocophillips Indonesia Inc. (Natuna) | Q4 - 2014 | Gas: 120 MMSCFD |
| Liquid: 1000 BPD | ||||
| Source: SKKMIGAS | ||||