TABLE: PLN's tender plan for IPP projects in eastern Indonesia
Thursday, April 22 2010 - 03:08 AM WIB
The following is the table of state owned electricity firm PT Perusahaan Listrik Negara's (PLN) tender plan for Independent Power Producer (IPP) projects in eastern Indonesia region, as unveiled by the firm during the hearing with the House of Representatives's Commission VII on April 21, 2010:
| No | Name of Project | Capacity (MW) | Start Bidding (PQ) | Power Purchase Agreement (PPA) Target | Target (COD) | Remark |
| 1 | PLTGU Bangkanai | 1x120 | April 2010 | Q II 2011 | 2015 | FTP2 - RUPTL |
| 2 | PLTU Kendari | 2x25 | April 2010 | Q II 2011 | 2014 | FTP2 - RUPTL |
| 3 | PLTU E. Kalimantan | 2x100 | April 2010 | Q II 2011 | 2015 | FTP2 - RUPTL |
| 4 | PLTU S. Kalimantan | 2x100 | May 2010 | Q II 2011 | 2015 | FTP2 - RUPTL |
| 5 | PLTP Lahendong 5&6 (PGE) | 2x20 | April 2010 | Q IV 2020 | 2014 | FTP2 - RUPTL |
| Note: PLTGU= Combined-cycle power plant; PLTP= Geothermal power plant; PLTU= Coal-fired power plant | ||||||