TABLE: PLN's tender plan for IPP projects in Java-Bali
Thursday, April 22 2010 - 03:02 AM WIB
The following is the table of state owned electricity firm PT Perusahaan Listrik Negara's (PLN) tender plan for Independent Power Producers (IPP) projects in Java-Bali region as unveiled by the firm during the hearing with the House of Representatives's Commission VII on April 21, 2010:
| No | Name of Project | Capacity (MW) | Start Bidding (PQ) | Power Purchase Agreement (PPA) Target | Target (COD) | Remark |
| 1 | PLTU Madura | 1x400 | June 2010 | Q II 2011 | 2015 | FTP2 - RUPTL |
| 2 | PLTP Kamojang (PGE) | 40x60 | April 2010 | Q IV 2010 | 2013 | FTP2 - RUPTL |
| 3 | PLTP Karaha (PGE) | 140 | April 2010 | Q IV 2010 | 2013 | FTP2 - RUPTL |