TABLE: PLN's tender plan for IPP projects in western Indonesia
Thursday, April 22 2010 - 03:05 AM WIB
The following is the table of state owned electricity firm PT Perusahaan Listrik Negara's (PLN) tender plan for independent power producer (IPP) projects in western Indonesia region, as unveiled by the firm during the hearing with the House of Representatives' Commission VII on April 21, 2010:
| No |
Name of Project |
Capacity (MW) | Start Bidding (PQ) | ?Power Purchase Agreement (PPA) Target | Target (COD) | Remark |
| 1 | PLTU MT S.Sumatra-6 | 2x300 | April 2010 | Q II 2011 | 2015 | RUPTL |
| 2 | PLTU MT Riau | 2x300 | April 2010 | Q III 2011 | 2016 | RUPTL |
| 3 | PLTU MT W.Sumatra-1 | 2x110 | May 2010 | Q II 2011 | 2015 | RUPTL |
| 4 | PLTU MT S.Sumatra-5 | 2x150 | May 2010 | Q II 2011 | 2015 | RUPTL |
| 5 | PLTU MT S.Sumatra-7 | 2x150 | May 2010 | Q II 2011 | 2015 | RUPTL |
| 6 | PLTU New Bangka 2 | 2x30 | May 2010 | Q II 2011 | 2014 | FTP 2 - RUPTL |
| 7 | PLTP Lumut Balai? (PGE) | 4x55 | April 2010 | Q IV 2010 | 2013 | FTP 2 - UPTL |
| 8 | PLTP Ulubelu (PGE) | 2x55 | April 2010 | Q IV 2010 | 2013 | FTP 2 - RUPTL |
| 9 | PLTA Simpang Aur | 29 | May 2010 | Q II 2011 | 2015 | FTP 2 - RUPTL |
| 10 | PLTA Lawe Mamas | 3x30 | May 2010 | Q II 2011 | 2016 | RUPTL |
| Note: PLTP= Geothermal power plant; PLTA= Hydro power plant; PLTU= Coal-fired power plant | ||||||