Table: PoD/PoP for 2012 period approved by BPMIGAS

Thursday, March 22 2012 - 09:47 AM WIB

Below is the list of PoD/PoP submitted by oil, gas contractors(s) throughout 2012 that have been approved by Upstream authority BPMIGAS.(ed)

No Project Contractor (s) Target on stream Production  on 2012

Explanation

Oil (BOPD) Gas (MMSCFD)
1 POP AP NEA      PHE ONWJ 1-Jan-12 - 50 -
2 POP Wortel 3 Santos (Sampang) Ltd. 19-Feb-12 120 20 -
3 POP Wortel 4 Santos (Sampang) Ltd. 1-Feb-12 50 10 -
4 POP Tembang-8  Indonesia ConocoPhillips 11-Mar-12 -      30 -
5 POP APN EB PHE ONWJ Mar-12 - 18 APBN EB & APN F Still waiting for topside improvement
6 POP APN F PHE ONWJ Mar-12 - 20
7 POD Tunu 13C Total E&P Indonesia Mar-12 818 - -
8 POD Terang-Serasun-Batur Dev.1 Kangean Energy Indonesia Jun-12 - 225 -
9 POD Tonga field Mosesa Apr-12 1.090 - Still waiting for land borrow and use permit & road access in Tonga field
10 POP Anoa WL-5X Premier Oil Apr-12 - 17 Is an enhancement of WL-5 well

11 POP Karang Enggal-2ST Pertamina EP Mei-12 178 0,8 Still in the process of Flowline installment
12 Project Removal of Gas Turbine Generator CNOOC Jun-12 2667 - -
13 POD Ridho-1 PT. Odira Energi Karang Agung Jun-12 667 - -
14 POD Tegal Pancing (TGP-1) Pertamina EP Jun-12 - 1.5 Still waiting for gas buyers
15 POD KE-38B & KE-54 Platform PHE WMO Jul-12 1.500 - -
16 POP Bawal Subsea ConocoPhillips Indonesia Jul-12 - 60 -
17 POP South Bungoh-1 well JOB PPEJ Jul-12 - 0,3 On schedule, but the on stream date will depend on Gas Purchase Agreement with a Gresik administration-owned company (BUMD)
18 POP North West Belani-1 Seleraya Jun-12 68 - Delayed from January 2012 to June 2012, because of a land dispute for the installment of Flowline
19 POP POP North Klalin-01 well PetroChina Int. (Bermuda) Ltd Jul-12 150 3,0 Still waiting for SKPP/SKPI certifications
20 POD South Mahakam 1 & 2 Total E&P Indonesia Agust-12 12.500 104

-

21 POP Vita Laras A-01 well CNOOC Agust-12 386 - Still waiting for AMDAL clearance, well not yet drilled
22 POP Karang luhur-1 well Pertamina EP Agust-12 225 2,5 -
23 POP Tasim-4 well Pertamina EP Agust-12 1.100 - -
24 POP Panen Utara-1 PetroChina Jabung Agust-12 500 0,7 Still waiting for land borrow and use permit
25 Peciko 78 Extension Total E&P Indonesia Sep-12 - 41 -
26 KF Gas Booster Compressor Star Energy kakap Ltd Sep-12 - 3,3 -
27 POP Cikarang-1 well Pertamina EP Jun-12 - 1,5 Still waiting for gas buyers
28 POFD Melibur Kondur Petroleum Sep-12 - 0,3 -
29 POP Pondok Berkah-1ST Pertamina EP Sep-12 194 2,6 -
30 POFD Air Hitam JOB PGSIL Sep-12 85 - -
31 POD West Seno Phase I Chevron Makassar Sep-12 714 - -
32 POD Rindu Area 6 (Dun) Chevron Pacific Indonesia Sep-12 874 - -
33 POD Bayan A MKI Okt-12 110 6,1 -
34 POP Hari-2 well ConocoPhilips South Jambi

Okt-12 12 0,6 -
35 POP Lamaru-1 well VICO Indonesia Okt-12 - 0.8 -
36 POP Tiung Biru-1st well Pertamina EP Okt-12 52 -  Still being processed at the exploration division at PEP
37 POED Kenali Asam Pertamina EP Okt-12 190 - -
38 POD WB - SB Non Asso Gas PetroChina Jabung Okt-12 1.000 20 Delayed from August 2012 estimate to October 2012, waiting for price agreement with PT PLN
39 POP NCJ-B1 Pertamina EP Okt-12 - 1,5 -
40 POFD Kampung Baru EPIC Sengkang Nop-12 - 4,5 -
41 POP Bobara Putih-1 Pertamina EP Nop-12 - - -
42 POD Budi Tately.N.V Nop-12 80 - -
43 Seng Gas Plant Phase -2 Kalila Bentu Ltd Des-12 - 30 -
44 Nubi 2A Extension Total E&P Indonesie Des-12 - 10 -
45 POFD Tempino (EOR) Pertamina EP Des-12 482 - -
46 POFO Dun Area 8 Rindu Chevron Pacific Indonesia Des-12 14 - -
  TOTAL     25.825 685  

Source: BPMIGAS