Table: Progess of PLN's power plant projects outside Java

Thursday, February 11 2010 - 08:51 AM WIB

PROJECT

CAPACITY (MW)

PROGRESS

EXPECTED OPERATION

ESTIMATED COD

2009 2010 2011 2012 UNIT - 1 UNIT - 2
1 PLTU NAD MEULABOH 2 x 110 MW 18 % - - 220 - May 2011 Aug 2011
2 PLTU 2 SUMUT PANGKALAN SUSU 2 x 220 MW 40% - - 440 - Mar 2011 Jun 2011
3 PLTU 1 RIAU BENGKALIS 2 x 10 MW 1% - - 20 - Oct 2011 Dec 2011
4 PLTU 2 RIAU SELAT PANJANG 2 x 7 MW 1% - - 14 - Aug 2011 Oct 2011
5 PLTU KEP. RIAU TANJUNG BALAI KARIMUN 2 x 7 MW 74% - 7 7 - Nov 2011 Jan 2011
6 PLTU SUMBAR TELUK SIRIH 2 x 112 MW 7% - - - 224 Jan 2012 Apr 2012
7 PLTU 3 BABEL BANGKA BARU 2 x 30 MW 54% - 30 30 - Nov 2010 Jan 2011
8 PLTU 4 BABEL BELITUNG 2 x 16.5 MW 7% - - 33 - Apr 2011 Jun 2011
9 PLTU LAMPUNG TARAHAN BARU 2 x 100 MW 36% - - 200 - Jun 2011 Sep 2011

10

PLTU 1 KALBAR PARIT BARU 2 x 50 MW 0% - - 50 50 Dec 2011 Feb 2011
11 PLTU 2 KALBAR BENGKAYAN 2 x 27.5 MW 1% - - 27.5 27.5 Dec 2011 Feb 2012
12 PLTU KALSEL ASAM-ASAM 2 x 65 MW 27% - - 130 - Feb 2011 Apr 2011
13 PLTU 1 KALTENG PULANG PISAU 2 x 60 MW 2% - - 120 -

TERMINATION

14 PLTU GORONTALO GORONTALO 2 x 25 MW 37% - - 50 - Apr 2011 Jun 2011
15 PLTU 2 SULUT AMURANG 2 x 25 MW 59% - - 25 25 Jan 2011 Mar 2011
16 PLTU SULAWESI TENGGARA NI TANAS / KENDARI 2 x 10 MW 71% - 10 10 - Dec 2010 Feb 2010
17 PLTU SULAWESI SELATAN BARRU 2 x 50 MW 56% - - 100 - Aug 2011 Oct 2011
18 PLTU 1 NTB BIMA 2 x 10 MW 8% - - 20 - Jul 2011 Sep 2011
19 PLTU 2 NTB LOMBOK 2 x 25 MW 5% - - 50 - Oct 2011 Dec 2010
20 PLTU 1 NTT ENDE 2 x 7 MW 79% - 14 - - Oct 2010 Dec 2010
21 PLTU 2 NTT KUPANG 2 x 16.5 MW 10% - - 33 - Aug 2011 Oct 2011
22 PLTU MALUKU UTARA TIDORE 2 x 8 MW 24% - - 16 - Oct 2011 Dec 2011
23 PLTU MALUKU AMBON 2 x 15 MW 0% - - - 30 RETENDER
24 PLTU 1 PAPUA TIMIKA 2 x 7 MW 0% - - - 14 RETENDER
25 PLTU 2 PAPUA JAYAPURA 2 x 10 MW 16% - - 20 - May 2011 Jul 2011
TOTAL 2,047 MW ? ? 61 1,616 371 ? ?
Source: PLN Parliamentary hearing Feb 11, 2010