Table; Progress of FTP -1 Program
Wednesday, May 31 2017 - 03:15 PM WIB
| No | Owner | Type | Name of Power Plant | Total Capacity (MW) | COD RUPTL 2017-2026 | COD Estimate | Details of Status and Progress | Follow-up Action |
| Kalimantan | ||||||||
| 1 | PLN | PLTU | Pulang Pisau #2 | 1x60 | 2017 | July 2017 | * Unit 2 Performance Test process * Current physical progress 93.25% |
* Follow up action installing Water Trap in drainage channels for water processing at the drainage |
| 2 | PLN | PLTU | Parit Baru | 2x50 | 2017 2018 |
October 2017 December 2017 |
* Sub-contractor terminated * Proyek continued by existing contractor, plan surety bond * Physical progress 85% |
* Replace subcontractor with SUMEC(start June 2017) * Financial obstacle of contractor resolved through provision of retention payment TOC 2.5% covered by bank guarantee |
| 3 | PLN | PLTU | PLTU 2 KALBAR Bengkayang | 2x27.5 | 2018 2019 |
April 2018 June 2018 |
* Process to issue L/C to vendor. Contractor has made commitment to complete the project in 10-12 months after L/C. * Physical progress 81% |
* Financial obstacle of contractor resolved through direct payment to sub vendor and provision of retention TOC 5% covered by bank guarantee. |
| SULAWESI & NUSRA | ||||||||
| 4 | PLN | PLTU | Gorontalo | 2x25 | 2017 | Nov 2017 Feb 2018 |
* Current overall progressi 53.62% * Provision of transformer : estimate of GT and UAT onsite 21 July 2017, as alternative survey has been conducted for the lending of transformer 20kv/6.3kv at the PLTU Jeranjang project tin NTB * Sub-contractor for CW Pump House and Intake works is onsite and currently currently making preparations for excavation & land clearing |
* Project continued and has been proposed to be excluded from list of stalled projects |
| 5 | PLN | PLTU | Lombok #2 | 1x25 | 2017 | Jun-2017 | * Unit #2 has undergone chemical cleaning and currently at the stage of preparation for steam blow. Overall progress 92.54 | * Along with the sedimentation at the water intake and the entry of garbage into the debris filter. Follow up action : Currently tender in progress for work to expand capacity of intake and pump house |
| 6 | PLN | PLTU | Kode (FTP1) #2 | 7 | - | Jun-17 | Unit 2 : - Cleansing of fly ash at the flue gas duct -Inspection of function of teat alarm control panel cjorine system -Completing punch list construction Repair of metering panel door & synchronize system CCR: Additional progress 3.82% |
|
| 7 | PLN | PLTU | Bima (FTP1) | 2x10 | 2018 | Oct 2018 Dec 2018 | * Initial contractor terminated. No construction work. Progress prior to termination 79.45% * Additional progress 3.82% |
* Assessesment of materials from previous contractor required * Evaluation of project |
| MALUKU & PAPUA | ||||||||
| 8 | PLN | PLTU | Waai/Ambon | 2x15 | 2019 | 2018 | -Project has been suspended since 25 February 2014 and performance security has expired since 23 October 2013 (not extended). Last physical progress 66.79% | * Declared for Forfeiture (taling over of project) and assigned to subsidiary/Arbikas. * Assigned subsidiary (PT PJB) to complete the project (21 Apr 2017) * Made request for cost verification with BPKP on 21 Feb 2017 and expose 6 March 2017. |
| 9 | PLN | PLTU | Jayapura ? Holtekamp #1 | 1x10 | 2017 | May 2017 | -Process of realibility run test. Targeted to be completed on 20 May 2017 | |
| Source: PT. PLN | ||||||||