Table: Progress of PLN's power plant projects in Java

Thursday, February 11 2010 - 08:47 AM WIB

PROJECT

CAPACITY (MW)

PROGRESS

EXPECTED OPERATION

ESTIMATED COD

2009 2010 2011 2012 2013 UNIT - 1 UNIT - 2 UNIT-3
1 PLTU 1 BANTEN SURALAYA 1 x 625 MW 90% - 625 - - - May-2010 ? ?
2 PLTU 2 BANTEN LABUHAN 2 x 300 MW 99% 300 300 - - - Oct-2009 Feb-2010 ?
3 PLTU 3 BANTEN LONTAR / TL NAGA 3 x 315 MW 64% - - 945 - - Feb-2011 May-2011 Aug-2011
4 PLTU 1 JABAR INDRAMAYU 3 x 300 MW 81% - 990 - - - Jun-2010 Sep-2010 Dec-2010
5 PLTU 2 JABAR PELABUHAN RATU 3 x 350 MW 60% - - 1.050 - - Feb-2011 May-2011 Aug 2011
6 PLTU 1 JATENG REMBANG 2 x 315 MW 89% - 630 - - - Feb-2010 May-2010 ?
7 PLTU 2 JATENG ADIPALA 1 x 660 MW 0% - - - - 660 Dec-2013 ? ?
8 PLTU 1 JATIM PACITAN 2 x 315 MW 75% - - 630 - - Feb-2011 May-2011 ?
9 PLTU 2 JATIM PAITON 1 x 660 MW 83% - 660 - - - Jun 2010 ? ?

10

PLTU 3 JATIM TJ AWAR-AWAR 2 x 350 MW 6% - - - 700 - Jul-2012 Oct-2012 ?
TOTAL 7,490 MW ? 300 3,205 2,625 700 660 ? ? ?

Source: PLN Parliamentary hearing Feb 11, 2010