Table: Realization of 2015 onstream projects as of Sept. 30, 2015
Monday, October 19 2015 - 10:33 AM WIB
The following is the list of oil and gas projects that have come onstream as of Sept. 30, 2015 as unveiled by SKK Migas
| No | PSCs | Projects | Production facility capacities | Onstream targets | Remarks | ||
| Liquid (bpd) | Gas (mmscfd) | Quarter | Year | ||||
| 1. | Premier Oil Natuna Sea B.V | Pelikan Development | 0 | 100 | Q1 | 2015 | Onstream March 9, 2015 |
| 2. | Petronas Carigali Ketapang 2 Ltd (PCK 2L) | Bukit Tua Development | 20,000 | 70 | Q2 | 2015 | Onstream May 18, 2015, now producing 5,503 bopd |
| 3. | JOB Pertamina Medco E&P Tomori | Senoro Gas Development | 11,000 | 310 | Q2 | 2015 | Train 1 CPP has started production and ramped up production to DSLNG May 29, 2015 Production from Train 2 on July 20, 2015, ramped up to 100 mmcfd July 27, 2015 |
| 4. | Total E&P Indonesie | South Mahakam Dev. 3 (Jempang Metulang 1) | 1,800 | 120 | Q3 | 2015 | Onstream July 10, 2015 |
| 5. | ConocoPhillips (Grissik) Ltd | Suban Mid-term Water Disposal | 0 | 0 | Q3 | 2015 | Onstream / injection to well #7 and #8 end-May 2015 |
| 6. | Petronas Carigali Muriah Ltd (PCML) | Kepodang Development | 0 | 145 | Q4 | 2015 | Onstream Agustus 2015 |
| 7. | Total E&P Indonesie | Bekapai Phase 2B Facilities Modification | 2,039 | 29.2 | Q3 | 2015 | Onstream Sept. 13, 2015 |
| Source: SKK Migas | |||||||