Table: SKK Migas updates progress of 2015 oil, gas projects
Thursday, July 9 2015 - 04:03 AM WIB
The following is the list of oil and gas projects already onstream in first semester of 2015 and scheduled to come onstream in second semester of 2015 as unveiled by SKK Migas
| Projects Onstream in 2015 (Realization as of Semester I) | |||||||
| No | PSCs | Project | Capacity of Production Facility | Onstream Target | Description | ||
| Liquid (bpd) | Gas (MMscfd) | Quarter | Year | ||||
| 1 | Premier Oil Natuna Sea B.V | Pelikan Development | 0 | 100 | Q1 | 2015 | Has been onstream since March 9, 2015 |
| 2 | Petronas Carigali Ketapang 2 Ltd (PCK2L) | Bukit Tua Development | 20,000 | 70 | Q2 | 2015 | Has been oonstream since May 18, 2015, current production stands at a rate of 5,503 bopd. |
| 3 | JOB Pertamina Medco E&P Tomori | Senoro Gas Development | 11,000 | 310 | Q2 | 2015 | Fist Production from CPP has started ramping up to DSLNG on Mei 29, 2015 |
| Projects Onstream in 2015 (Outlook for Semester II) | |||||||
| 1 | EMP Tonga (Mosesa) | Receiving Tank Facility | 2,000 | 0 | Q3 | 2015 | Project progress at 71.8% (actual) Vs 88.09% plan |
| 2 | EMP Tonga (Mosesa) | Sintong Offloading Facility | 2,000 | 0 | Q3 | 2015 | Project on-hold because of oil price drop |
| 3 | ConocoPhilips | Suban Mid Term Water Disposal | 0 | 0 | Q3 | 2015 | Currently at the commissioning stage (per April 2015) |
| 4 | Total E&P Indonesie | South Mahakam Dev. 3 (Jempang Metulang 1) | 1,800 | 120 | Q3 | 2015 | Platform was ready for drilling on 21 April 2015. Currently in the process of drilling. |
| 5 | Total E&P Indonesie | Bekapai Phase 2B Facilities Modification | 2,039 | 29.2 | Q3 | 2015 | Currently at the stage of Offshore Compaign and preparation for pipeline installation. |
| 6 | ExxonMobil Cepu Ltd. | Banyu Urip | 185,000? | 124 | Q3 | 2015 | First Production Juli 2015, to peak in November 2015 |
| 7 | CNOOC | SES Gas Development (Asti-A) | 0 | 40 | Q4 | 2015 | Risked of being postponed to Q4 2015 due to unavailability of barge |
| 8 | CNOOC | SES Gas Development (Asti-A)?? | 0 | 40 | Q4 | 2015 | Risked of being postponed to Q4 2015 due to unavailability of barge |
| 9 | Petronas Carigali Muariah Ltd (PCML) | Kepodang Development | 0 | 145 | Q4 | 2015 | With upstream-downstream scheme:
- Upstream : Wellhead and CCP Platform carried out by PCML - Downstream : Gas Transportation Pipe and DRF carried out by PT KIG |
| Source: SKK Migas | |||||||