Tangguh LNG vessels ready to be delivered: BPMIGAS

Thursday, December 4 2008 - 08:20 AM WIB

Seven vessels which would operate solely to transport LNG from Tangguh LNG project, West Papua, to its customers across the globe had been successfully commissioned and ready to be delivered, upstream oil, gas authority BPMIGAS said on Thursday.

The tankers are constructed in South Korea by Samsung (three units), Hyundai (two units) and Daewoo (2 units).

Three of the tankers would be operated by Kawasaki Kisen Kaisha Ltd. Teekay LNG Partners and Sovcomflot/ NYK Line consortium will operate two tankers each.

Local partners will hold between 5-30 percent stakes in the tankers.

Meanwhile, BPMIGAS also said that Tangguh LNG project had entered commissioning stage with plant construction 96 percent completed and Gas Pipelines Feed construction 99.9 percent completed.

BPMIGAS also said that the Tangguh LNG had conducted nitrogen run test for compressors, which was part of the plant?s commissioning.

Tangguh LNG plant, which is operated by Anglo-American giant BP plc is expected to ship first LNG in April 2009. The plant, which will havae capacity of 7.6 MTPA, will supply LNG to its customers in China, South Korea, Mexico and Japan.(alex)

No Vessel Name Lead Consortium Share Operator Local Share Status
1 Tangguh Foja Kawasaki Kisen Kaisha Ltd (K Line) 95% K Line Meratus 5%
Delivery, 21 November 2008
Gas trials 6 - 25 July 2008
Sea Trials 17 - 21 June 2008
2 Tangguh Jaya Kawasaki Kisen Kaisha Ltd (K Line) 95% K Line Meratus 5% Delivery, 29 December 2008
Gas trials 11 - 28 Oct 2008
Sea Trials 17 - 21 Sept 2008
3 Tangguh Palung Kawasaki Kisen Kaisha Ltd (K Line) 95% K Line Meratus 5% Delivery, 2 March 2009
Gas trials 4 ? 21 Des 2008
Sea Trials 16 ? 20 Nov 2008
4 Tangguh Hiri Teekay LNG 70%
Teekay Berlian Laju Tanker 30% Delivery, 24 December 2008
Gas trials 31 Augt ? end Sept 2008
Sea Trials 21- 26 July 2008
5 Tangguh Sago Teekay LNG 70% Teekay Berlian Laju Tanker 30% Delivery, 14 May 2009
Gas trials 6 Des 2008 ? 08 Jan 2009
Sea Trials 6 Des 2008 ? 5 Jan 2009
6 Tangguh Towuti Sovcomflot/ NYK Line
75%
NYK Samudra Indonesia 25% Delivery, 07 December 2008
Gas trials 28 August ? 10 Sept 2008
Sea Trials 28 August ? 10 Sept 2008
7 Tangguh Batur Sovcomflot/ NYK Line
100%
NYK - Delivery, 30 January 2009
Gas trials 04-13 November 2008
Sea Trials 04-13 November 2008

Share this story

Tags:

Related News & Products