The tankers are constructed in South Korea by Samsung (three units), Hyundai (two units) and Daewoo (2 units).
Three of the tankers would be operated by Kawasaki Kisen Kaisha Ltd. Teekay LNG Partners and Sovcomflot/ NYK Line consortium will operate two tankers each.
Local partners will hold between 5-30 percent stakes in the tankers.
Meanwhile, BPMIGAS also said that Tangguh LNG project had entered commissioning stage with plant construction 96 percent completed and Gas Pipelines Feed construction 99.9 percent completed.
BPMIGAS also said that the Tangguh LNG had conducted nitrogen run test for compressors, which was part of the plant?s commissioning.
Tangguh LNG plant, which is operated by Anglo-American giant BP plc is expected to ship first LNG in April 2009. The plant, which will havae capacity of 7.6 MTPA, will supply LNG to its customers in China, South Korea, Mexico and Japan.(alex)
No | Vessel Name | Lead Consortium Share | Operator | Local Share | Status |
1 | Tangguh Foja | Kawasaki Kisen Kaisha Ltd (K Line) 95% | K Line | Meratus 5% |
Delivery, 21 November 2008 Gas trials 6 - 25 July 2008 Sea Trials 17 - 21 June 2008 |
2 | Tangguh Jaya | Kawasaki Kisen Kaisha Ltd (K Line) 95% | K Line | Meratus 5% | Delivery, 29 December 2008 Gas trials 11 - 28 Oct 2008 Sea Trials 17 - 21 Sept 2008 |
3 | Tangguh Palung | Kawasaki Kisen Kaisha Ltd (K Line) 95% | K Line | Meratus 5% | Delivery, 2 March 2009 Gas trials 4 ? 21 Des 2008 Sea Trials 16 ? 20 Nov 2008 |
4 | Tangguh Hiri | Teekay LNG 70% |
Teekay | Berlian Laju Tanker 30% | Delivery, 24 December 2008 Gas trials 31 Augt ? end Sept 2008 Sea Trials 21- 26 July 2008 |
5 | Tangguh Sago | Teekay LNG 70% | Teekay | Berlian Laju Tanker 30% | Delivery, 14 May 2009 Gas trials 6 Des 2008 ? 08 Jan 2009 Sea Trials 6 Des 2008 ? 5 Jan 2009 |
6 | Tangguh Towuti | Sovcomflot/ NYK Line 75% |
NYK | Samudra Indonesia 25% | Delivery, 07 December 2008 Gas trials 28 August ? 10 Sept 2008 Sea Trials 28 August ? 10 Sept 2008 |
7 | Tangguh Batur | Sovcomflot/ NYK Line 100% |