Tender process of three power projects continues: PLN
Wednesday, January 17 2007 - 01:43 AM WIB
Eddie said that that PLN did not have any plan to retender them because the existing bidders had indicated their strong commitment to provide financial guarantee to finance the projects.
"We will still give them a chance because they have given certainty that they would be able to secure the funding for the projects," he said.
Jusuf Kalla urged PLN Monday to retender the three projects because the existing bidders lacked financial backing to finance the projects.
Consortium China National Machinery Industry Corp - Sinomach - PT Penta Adi Samudra was the only consortium left in tender for Tanjung Awar Awar power plant, Indramayu power plant and consortium Chengda Engineering Corp -Truba Jurong Engineering were the potential winners to build Labuhan power plant.
PLN expected to sign contracts with the winners of the Labuhan, Tanjung Awar-Awar and Indramayu projects in February this year. (Godang)