Total?s platform at Nubi 2B installed
Monday, March 3 2014 - 02:08 AM WIB
By Febry Silaban
Total EP Indonesie (TEPI), a subsidiary of French firm Total SA, said its WPN3 platform at Nubi 2B with a capacity of 150 mmscfd has been installed.
?Currently the drilling activity is ongoing in Nubi,? TEPI?s Head of Media Relations Kristanto Hartadi told Petromindo.com on Thursday, adding the drilling started in the end of last week.
Meanwhile, he added, the installation of WPS2 platform at Sisi with the capacity of 200 mmscfd and the SWP-J platform in Peciko with a capacity of 150 mmscfd will be completed in the coming weeks, which will be followed by drilling activities.
?The production is expected to begin in the second quarter of this year,? Kristanto said.
Editing by Johannes Simbolon