US$10 billion energy projects, deals signed and inaugurated
Tuesday, October 30 2007 - 07:14 AM WIB
The President inaugurated the operation of new oil and gas wells in Oyong field controlled by Australian firm Santos Limited and in Ujung Pangkah field controlled by American firm Hess Corporation.
According to the Ministry of Energy and Mineral Resources, Ujung Pangkah now produces 100 MMCFD of gas and 1,800 barrels per day of condensate. The firm will invest a total of $930 million to develop the field, including $230 million in the current Phase I development and $700 million the Phase II development. The Phase I development will boost Ujung Pangkah?s oil and condensate output to 25,000 bpd and enable it to produce LPG as much as 6,000 barrels of oil equivalent per day in 2009.
Meanwhile, Oyong field now produces between 8,000 and 10,000 barrels per day of oil and will produce 60 MMCFD of gas in 2009. Santos?s spending for the development of the field will total $212.6 million, including $16.4 million in capital expenditure and $196.2 million in operation expenditure.
During the ceremony, Susilo together with Minister of Energy and Mineral Resources Purnomo Yusgiantoro also witnessed the signing of 12 gas sales and purchase agreements. The 12 agreements are as follows:
| No | Buyer | Seller | Form of Agreement | Length/ Start of Contract | Flow Rate (BBTUD) | Contract Volume (TBTU) | Contract Value (Million US$) |
| 1 | PT PLN Gresik | Kangean Energi Indonesia Ltd. |
GSPA Amendment |
18 years / 2010 |
- |
369 | 1364 |
| 2 | PT Pertagas | Kangean Energi Indonesia Ltd. |
GSPA Amendment |
10 years / 2010 |
- |
220.9 |
806.01 |
| 3 | PT Indogas Kriya Dwiguna | Kangean Energi Indonesia Ltd. | GSPA Amendment | 11 years / 2010 |
- |
79.241 |
293.19 |
| 4 | PT.Riau Andalan Pulp & Papers | Kalila Bentu | GSPA | 14 years / 2007 |
- |
84.5 |
381.09 |
| 5 | PT. Petrokimia Gresik | PT Kangean Energi Indonesia Ltd. | GSPA Amendment |
20 years / 2010 |
- |
188.9 |
646.63 |
| 6 | PT Energasindo Heksa Karya for PLTG Payo Selincah, Jambi |
ConocoPhillips (Grissik) | GSPA |
8 years / 2008 |
- |
65.7 |
269.13 |
| 7 | PT Energasindo Heksa Karya for Industries in Medan, North Sumatra |
JOB Pertamina Costa (Int'l) |
HoA |
8 years / 2008 |
- |
24.147 |
129.54 |
| 8 | PT Pupuk Iskandar Muda | Medco Malaka |
HoA |
7 years / 2010 |
- |
200.6 |
1,043.45 |
| 9 | PT Gasuma Corporindo for electricity in East Java | PT Pertamina EP, PetroChina International Java Ltd and Medco Tuban |
GSPA |
6 years / 2008 |
- |
13.14 |
21.02 |
| 10 | PT Inti Alasindo Energy | Husky Oil (Madura) Ltd. | GSPA | 20 years / 2012 |
- |
170.40 | 734.40 |
| 11 | PT Parna Raya | Husky Oil (Madura) Ltd. | GSPA | 20 years / 2012 |
- |
170.40 | 734.40 |
| 12 | PT PGN Tbk. | Husky Oil (Madura) Ltd. | GSPA | 20 years / 2012 |
- |
85.20 |
367.20 |
|
Total
|
1672.128 |
6790.39 |
|||||
| Note:GSPA= Gas sales and purchase agreement; HoA= Head of Agreement | |||||||
Susilo also witnessed the signing of 10 power plant projects, consisting of five independent power producer (IPP) projects and five ?10,000 MW-crash program? power projects. The power projects are as folows:
|
No |
Projects |
Location |
IPPs |
Investment Value (US$ million) |
| 1 | Molobatu coal fired power plant (2x10 MW) |
Gorontalo | PT Tenaga Listrik Gorontalo | 20 |
| 2 | Kaltim coal-fired power plant (2x25 MW) | East Kalimantan |
PT Indo Ridlatama | 50 |
| 3 | Poso hydro power plant (3x65 MW) | Poso, Central Sulawesi | PT Poso Energy | 398.5 |
| 4 | Baturaja coal-fired power plant ( 2x112.5 MW) | South Sumatra | PT Priamanaya Djan International |
225 |
| 5 | Sarulla geothermal power plant (3x110 MW) | North Sumatra | PT Medco Energi Internsional, Ormart, Itochu Corp. | 527 |
| Total |
1,220 |
|||
|
No |
Govt's project under 10,000 MW program |
Location |
Developer(s) |
Investment Value (US$ million) |
| 1 |
NTB coal-fired power plant (2x25 MW) |
West Nusa Tenggara | PT Barata Indonesia | 69 |
| 2 | Sulut coal-fired power plant (2x25 MW) | Minahasa, North Sulawesi | PT Wijaya Karya | 79.9 |
| 3 | Gorontalo coal-fired power plant (2x25 MW) | Gorontalo | PT Meta Epsi | 71.35 |
| 4 | Lampung coal-fired power plant (2x100 MW) | Lampung | PT Adhi Karya and Jiangxi Electrical Power Design Institute | 220 |
| 5 | Sumut coal-fired power plant (2x200 MW) | North Sumatra | Consortium of Guangdong Power Engineering Corp-PT Nincec Multi Dimensi-PT Bagus Karya | 383 |
| Total |
824.4 |
|||