At least 19 smelters will begin operation within next five years: Govt

Wednesday, February 22 2012 - 02:45 AM WIB

At least 19 metal processing and refining facilities are currently either under construction or subject to feasibility study as part the country?s efforts to comply with a law banning ore exports beginning 2014, the Energy and Mineral Resources Ministry has reported.

Of the 19 facilities, seven are now in the construction phase, six under examination for feasibility and the remaining six have just obtained construction permits. Those facilities will begin commercial operations between 2012 and 2017, The Jakarta Post reported on Wednesday.

This year, an iron smelter producing sponge iron with a total production capacity of 500,000 tons per year will begin operation. The smelter is being built by Indoferro, said minerals and coal director general Thamrin Sihite in Jakarta on Tuesday.

The construction of the processing and refining facilities is part of the mining industry?s efforts to meet the requirement of the 2009 Law on Minerals and Coal, which has ordered a stop to ore exports in two years? time.

The requirement is contained in the 2012 ministerial regulation on added value for mineral commodities through processing and refining; which was issued recently as part of the implementation of the law.

The regulation sets minimum limits of mineral content in processed products for export. For instance, for copper, gold and silver the limit is 99 percent. ?This policy aims to conserve our natural resources as well as improve their economic benefits. If the ores are refined, their value will increase. The presence of smelters will also provide job opportunities for locals;? Thamrin explained.

According to the ministry?s data, state miner PT Aneka Tambang (Antam) plans to build four smelters in Halmahera, North Maluku (ferronickel); Mandiodo, Southeast Sulawesi (nickel pig iron); Mempawah, West Kalimantan (smelting grade alumina); and Gresik, East Java (gold, silver and copper).

However, the Gresik project has been suspended due to the results of a study that says the project is not economical.

State steel-maker PT Krakatau steel and Korea-based Posco have also teamed up to build a production plant in Cilegon, Banten, with a total production of 3.5 million tons of steel plate, 2.5 million tons of steel slab and 3 million tons of hot-rolled coil steel per year.

Nickel producer PT Vale Indonesia is now conducting a feasibility study for building a smelter in Pomalaa, Southeast Sulawesi, with a production capacity of 48.800 tons per year. The smelter is projected to begin operation in 2017.

Regarding coal in Prabumulih, South Sumatra, Pendopo Coal Gasification and Pendopo Coal Upgrading are also conducting feasibility studies for coal gasification and coal upgrading facilities. The coal gasification is expected to start in 2016 and the coal upgrading in 2013.

As reported earlier, the government has given three months for all mineral mining companies in the country to submit comprehensive proposals on their strategies to comply with the 2014 ore-export ban.

The proposals must include how they will process and refine their raw commodities, whether they will build their own smelters, cooperate with other companies to build smelters or refine their ore in external smelting plants. (*)

No Company Location Product Production Capacity Operation
1 PT Aneka Tambang Halmahera North Maluku Ferronikel 27.000 tons of FeNy/year 2014
2 PT Aneka Tambang Mandiodo, North Konawe,Southeast Sulawesi Nickel Pig Iron 120.000 tons/year 2014
3 PT Aneka Tambang Mempawah,West Kalimantan Smelting Grade Alumina 1 million of SGA/year 2014
4 PT Indonesia Chemical Alumina(Ica) Tayan, West kalimantan Chemical Grad Alumina 300.000 tons of SGA/year
5 PT Vale Indonesia(inco) pomalaa,southeast sulawesi Nikel Hidroxide(Nio Dan Coo) 48,800 tons/year 2017
6 PT weda Bay Nikel Weda North Maluku Nikel Hidroxide(Nio Dan Coo) 60.000 tons/year 2016
7 meratur jaya iron& steel batu licin, South Kalimantan Sponge Iron 315.000 tons/year 2014
8 indoferro Cilegon , Banten Sponge Iron 500.000 tons/year 2012
9 PT Sebuku Iron Lateritic Sebuku, South Kalimantan Sponge Iron 1 million tons/year 2014
10 PT Kerakatau Steel Posco Cilegon , Banten Steel 3,5 million ton of plate/year

2,5 million ton of slap/year

3 million HRC/year

2014

11 PT Nusantara

Smelting

Bontang, East

Kalimantan

Copper Cathode 200.000 tons/year

2014

12 PT Aneka Tambang Gresik, East Java Gold, Silver,etc 2.000 tons/year ?
13 PT Indosmelt Maros, South Sulawesi Copper Cathode 100.000 tons of copper cathode, 200.000 tons of copper slag 2014
14 pendopo coal gasification Prabumulih, South Sumatra Coal Gasification ? 2016
15 pendopo coal up grading Prabumulih, South Sumatra Upgraded Coal 5 million tons/year 2013
16 PT Dairi Prima Mineral Dairi, North Sumatra Lead And Zinc Concentrate 110. 000 tons of lead/year and? 220.000 tons of zinc/ year 2014
17 PT Agincourt Resources South Tapanuli,North Sumatra Dore Bullion 250.000 tons of gold/year and 2,5 million tons of silver/year 2015
18 PT Jinghuang Indonesia Morowali, Southeast Sulawesi Sponge Ferronikel 2 million tons/year ?
19 PT Timah Cilegon , Banten Tin Chemical 500.000 tons/year 2015

Source: Energy and Mineral Resources Ministry