UK Finders completes Wetar copper project scoping study

Monday, June 26 2006 - 07:55 PM WIB

UK miner Finders Resources said on Friday that scoping study it had conducted on Wetar copper project confirmed the economic viability of its 64 percent-owned project.

The company said that the base case scenario on the project involved key elements of an Indicated and Inferred Mineral Resource estimate of approximately 10.7 Mt, grading 2.4% copper, 0.6g/t gold and 27g/t silver at a cut-off grade of 0.5% copper. The average strip ratio is estimated as 0.67, with mining rate of approximately 1.25 Mtpa of ore, initially from the Kali Kuning deposit with Lerokis production commencing in year 3 with an approximate 9 year mine life.

The study indicated that the mine would be able to produce some 23,000 tpa of LME A-grade good delivery copper metal.

The study also suggested that production of a rough copper concentrate would be conducted at Wetar island. The concentrate would then be shipped to a suitable hydrometallurgical plant.

According to the company, the scoping study model uses a discount rate of 10% with no financial gearing and assumes US$1.50/lb copper; approximately 60% silver recovery, US$10/ ounce silver and zero gold recovery. Key results are as follows: (i) an approximate US$105 million project expenditure requirement to commence production, including project management costs and working capital; (ii) Component capital cost estimates are: Mining, concentrate production and infrastructure on Wetar: US$50 million and Offshore hydrometallurgy plant: US$40 million; (iii) Average cash operating costs of US$0.60/lb copper (after silver by product credits); (iv) operating cash flow of approximately US$300 million with a 2.5 year payback period and (v) a project net present value of US$90M based the application of a 10% per annum discount rate to ungeared after tax projected cash flows, and an internal rate of return of 34%

The company said that 2-stage feasibility studies on the project would commence immediately, to advance technical and commercial aspects of project development, with a view to commencing project construction in Q4 2007. Stage 1 of the proposed feasibility study will include detailed studies to finalize treatment process selection, which is estimated to take 3-6 months and followed by a formal bankable feasibility study, which is estimated to take between 9 and 15 months to complete.(alex)

Share this story

Tags:

Related News & Products