RE conducts land clearing for PLTGU Grati relocation in Bali
January 7, 2022
JSP to soon install gas turbine in PLTGU Jawa-1
August 24, 2020
PLTGU Lombok Peaker to fully operate at year-end
July 18, 2020
PLTGU Grati Add-on starts commercial operation
July 17, 2020
Construction progress PLTGU Riau reaches 80%
July 14, 2020
Construction progress of PLTGU Tambak Lorok project at 72%
July 13, 2020
Progress of PLTGU Jawa 1 project reaches 71%
May 14, 2020
Hanlim Power plans giant PLTGU project in N. Sumatra
March 10, 2020
Construction progress of PLTGU Jawa 1 reaches 65%
March 4, 2020
Construction progress of PLTGU Jawa 1 reaches 65%
March 4, 2020
PLN obtains location permit for PLTGU Luwuk project
February 17, 2020
Construction progress PLTGU Riau project reaches 56%
February 8, 2020
PLN operates PLTGU Tanjung Uncang in Batam
January 18, 2020
PLTGU Jawa-1 power plant construction 45.5% complete
December 12, 2019
PLTGU Muara Karang set to start operating in March 2020
December 2, 2019